It's not just scenery, it's everything else! - The newspaper

It was unlikely that other National Games would experience the same bad luck after the national embarrassment brought on by the Ibagué Games in 2015, which resulted in the arrest of about 20 people for embezzlement and the harm done to athletes and society. However, this time, the Ministry of Sport's laziness was to blame, not its own selfish motives. The issue now is that the shame is not foreign but local, and despite the cries for assistance issued by the forces of action, the Comptroller's Office, the media, and sports mourners so that the events in Eje Cafetero and Valle do not succumb, few have stopped to consider that the organization of a competition of this level encompasses much more than the sports facilities where each discipline will take place.
Because all of the public infrastructure in this country has historically been supported by improvisation and justifications, the Hispanic culture was astounded when officials in Qatar mentioned that the construction projects would be 70% complete in 2019. A letter from the departments and capital cities that are currently the host cities for the XXII edition of the Games for this year was sent on Friday the 13th, what a date, and it openly expressed their concern for the Ministry of Sport's silence and lack of interest in taking action against an athlete who, despite inheriting unethical practices, was thought to improve the situation. However, nothing changed as a result of Resolution 601 of 2020 and Conpes 4095 of 2022.
The confusion that the powers currently lack a general director, assistant director, and less technical director, further delaying schedules that are already behind schedule, was expressed in the letter that is also addressed to the president and the congressmen. Logistics are everything What made the hub shine 18 years ago when the South American U-20 tournament was organized were the throngs of mostly young university students, who were the perfect anchor between administrative decisions and the implementation of what had been planned.
This is covered in the letter that was produced by the departmental sports organizations' meeting in Caldas, Palestine, as well as in the letter's discussion of the event's logistics, which only a few people have noticed by thinking about the tracks, courts, and swimming pools. According to the letter, the regional socialization of the specialized implementation agreements has not yet taken place, which has prevented projections of purchases and clarity regarding the technical requirements, which had a $33 billion initial value, from being made.
The legality of this meeting is in jeopardy because there is no platform for long list registrations; instead, a manual was created by sport and modality. No one has bothered to ask athletes if they have hotel reservations or if they should change them because the venue in the city where they competed could not be prepared, despite the fact that they have pushed themselves to the limit in national and international competitions to improve their times.
While the 2024 Paris Olympics mascot, Astolfo, has a similar one with a prosthetic leg, Trochi does not in this instance of the Paranational Sports VI. In the letter, there was also concern for this competitive subset of people who also possessed additional skills.
There, they describe how they have adamantly demanded that Decree 520, which permits inclusive participation, be repealed. Due to a lack of clarity in their organizational structure and a lack of National Sports System regulation, six Paralympic sports run the risk of not having enough competitors to compete.
Conventional sports don't even have instructions, much less those that have different rules. The secretaries who signed the letter claim that the 77 percent figure used by the Comptroller to describe the length of the delay in the work is inaccurate because it did not account for December, when the tenders were awarded.
Fact The fact that the execution of the works is subject to a new review of the audits, despite the fact that they already have a favorable concept from the Ministry and the conservatorships that issue the construction licenses, causes annoyance in the territorial entities. Three of the 23 sports venues have projects that are technically feasible.
21 are currently in the structuring and revision stage. 12 projects are still in the structuring and review stages, with delays of between 10% and 30%.
The issue now is that the shame is not foreign but local, and despite the cries for assistance issued by the forces of action, the Comptroller's Office, the media, and sports mourners so that the events in Eje Cafetero and Valle do not succumb, few have stopped to consider that the organization of a competition of this level encompasses much more than the sports facilities where each discipline will take place.